Contracts in Progress

Contracts in progress are as follows at March 31, 2013 and December 31, 2012:
 
March 31,
2013
 
December 31,
2012
Costs incurred on uncompleted contracts
$
354,508

 
$
750,218

Estimated earnings
70,731

 
171,475

 
425,239

 
921,693

Less: Billings to date
(422,060
)
 
(918,817
)
 
$
3,179

 
$
2,876

Included in the accompanying consolidated balance sheet under the following captions:
 

 
 

Costs and estimated earnings in excess of billings on uncompleted contracts
20,363

 
$
19,245

Billings in excess of costs and estimated earnings on uncompleted contracts
(17,184
)
 
(16,369
)
 
$
3,179

 
$
2,876



Contract costs include all direct costs, such as materials and labor, and those indirect costs related to contract performance such as payroll taxes and insurance. Provisions for estimated losses on uncompleted contracts are made in the period in which such estimated losses are determined. Changes in job performance, job conditions and estimated profitability may result in revisions to costs and income and are recognized in the period in which the revisions are determined. An amount equal to contract costs attributable to claims is included in revenues when realization is probable and the amount can be reliably estimated.


us-gaap:LongTermContractsOrProgramsDisclosureTextBlock